Customize Consent Preferences

We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.

The cookies that are categorized as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ... 

Always Active

Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.

No cookies to display.

Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

No cookies to display.

Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.

No cookies to display.

Skip to content

Data Center D Shell and Build-out

Culperer, Virginia

Location

Culpeper, Virginia

Client

Confidential

Contract Value

$46,700,000

Square Feet

116,164

Year Completed

September 2015

Schedule

12 months

Key Partners

The M Group / Power Cool Engineers

Overview

Constructed as the largest data center on the Network Access Point (NAP) of the Capital Region's campus, the Data Center D project included cast-in-place foundation walls, a new two-story precast structure, and an elevated structural steel platform on the roof supporting critical mechanical cooling equipment and the chilled water piping loop.

 

Built in twelve months, the 116,164-sf space included 29,000 sf of white space and 2.4-MW of critical IT load.

The scope of work required the installation of three 2.5-MW generators, six 720-kW rotary uninterruptible power supplies (UPS), 24 static transfer switches (STS) / power distribution units (PDU), three 395-ton air-cooled chillers, six drycoolers for freecooling scenarios, three 100-horsepower variable / primary chilled water pumps, and 22 50-ton computer room air conditioning (CRAC) units.