Customize Consent Preferences

We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.

The cookies that are categorized as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ... 

Always Active

Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.

No cookies to display.

Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

No cookies to display.

Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.

No cookies to display.

Skip to content

Confidential Data Center Susquehanna

Berwick, Pennsylvania

Project Details

Location

Berwick, Pennsylvania

Client

Confidential

Contract Value

Confidential

Square Feet

280,000

Year Completed

2023

Schedule

 23 months

Key Partners

Highland Associates

Overview

This project was the erection of a cold dark shell composed of curtain walls, precast panels, steel framing, and ACM rainscreen paneling. Programmatic scope includes loading docks with overhead doors, two floors of administrative space, and an elevator. Campus development took place at a nuclear power plant site, including 34.5kV power distribution, 12.5kV power loop, underground sanitary, storm, and domestic water distribution.

 

Ancillary buildings included a well pump house and well, fire pump house, and a fire water storage tank. Exterior site work included roadways/hardscape and landscaping. Design-assist services were implemented throughout the project to ensure successful completion.

 

 

Our ExpertsOur ExpertsOur ExpertsOur Experts

Key Team Members

Evan Antonides

Co-President

Andre Grebenstein

Vice President & Office Leader

New York

John Fritz, Sr.

Vice President, Mission Critical

Washington, DC

You might be interested in...

2930 Corvin Drive Renovation
Confidential Data Center Project Cowboy