Customize Consent Preferences

We use cookies to help you navigate efficiently and perform certain functions. You will find detailed information about all cookies under each consent category below.

The cookies that are categorized as "Necessary" are stored on your browser as they are essential for enabling the basic functionalities of the site. ... 

Always Active

Necessary cookies are required to enable the basic features of this site, such as providing secure log-in or adjusting your consent preferences. These cookies do not store any personally identifiable data.

No cookies to display.

Functional cookies help perform certain functionalities like sharing the content of the website on social media platforms, collecting feedback, and other third-party features.

No cookies to display.

Analytical cookies are used to understand how visitors interact with the website. These cookies help provide information on metrics such as the number of visitors, bounce rate, traffic source, etc.

No cookies to display.

Performance cookies are used to understand and analyze the key performance indexes of the website which helps in delivering a better user experience for the visitors.

No cookies to display.

Advertisement cookies are used to provide visitors with customized advertisements based on the pages you visited previously and to analyze the effectiveness of the ad campaigns.

No cookies to display.

Skip to content

Microsoft Chevy Chase Headquarters

Chevy Chase, Maryland

Location

Chevy Chase, Maryland

Client

Microsoft Corporation

Contract Value

Confidential

Square Feet

60,000

Year Completed

2016

Schedule

28 weeks

Key Partners

SmithGroup

Project  Types

Office

Renovation

Awards & Certifications

  • ABC Metro Washington/Virginia Excellence in Construction, 2017
  • International Interior Design Association, Award of Merit, 2017

Overview

The Microsoft Chevy Chase office is one of the most prestigious of the company. This project consisted of two phases and consolidated all employees onto the fifth through seventh floors, returning the eighth and ninth floors to the landlord. Phase I included the construction of the fifth and sixth floors, while seven through nine were occupied. These floors included four pantries, a wellness room, and three reception desks. Phase II included the removal of the staircase from the seventh-eighth floors, pouring back the slab, decommissioning the eighth and ninth floors, and minor construction of the seventh floor.

During the preconstruction process, our team spent three weeks performing value engineering analysis and ultimately saved the client $117,000 in construction costs.

 

One of the unique architectural features of the project was the portal made from 100+-year-old reclaimed barn wood, which is eight feet tall with glass in the middle that changes colors. Our team completed the project three weeks ahead of schedule, going above and beyond the client’s expectations.